MCQ Questions Civil Engineering Construction Planning and Management

MCQ Questions Civil Engineering Construction Planning and Management-3

MCQ Questions Civil Engineering Construction Planning and Management

Take a look at these MCQ Questions Civil Engineering Construction Planning and Management interview questions and our tips on how to answer them. If you’re applying for an engineering internship, graduate scheme or entry-level job, you’ll face at least one interview as part of an engineering employer’s recruitment process. You may be interviewed by one or more members of the HR team, senior members of the engineering team you’d be joining or a mixture of both. In this section we will study MCQ Questions Civil Engineering Construction Planning and Management. 
As well as questions about your reasons for applying to the role and the employer in question, engineering recruiters will be assessing your potential in the areas that is crucial to any engineering role: technical expertise. Engineers may be asked to perform feats of fantastic technical prowess, but it will be as as part of a Justice League rather than as a solo engineering super hero.
 

The interviewer is almost as nervous as the candidate in most interviews. You might wonder if you look confident enough, if you will hire the right person, or if you are asking the right engineering interview questions. The last question is arguably the most crucial part to worry about when you’re interviewing candidates. Other topics on Civil Engineering Multiple Choice Questions can be accessed 

MCQ Questions Civil Engineering Construction Planning and Management - Set - 3

Question 1: 

Economic saving of time results by crashing
a) cheapest critical activity
b) cheapest non-critical activity
c) costliest critical activity
d) costliest non-critical activity

Correct Answer – (A)

Question 2 : 

The direct cost of a project with respect to normal time is
a) minimum
b) maximum
c) zero
d) infinite

Correct Answer – (A)

Question 3 : 

The time with which direct cost does not reduce with the increase in time is known as
a) crash time
b) normal time
c) optimistic time
d) standard time

Correct Answer – (B)

Question 4 : 

What estimate would you give for the variance in above problem ?
a) 81
b) 54
c) 36
d) 9

Correct Answer – (A)

Question 5 : 

The independent float affects only
a) preceding activities
b) succeeding activities
c) the particular activity involved
d) none of the above

Correct Answer – (C)

MCQ Questions Civil Engineering Construction Planning and Management

Question 6: 

The reduction in project time normally results in
a) decreasing the direct cost and increasing indirect cost
b) increasing the direct cost and decreasing the indirect cost
c) increasing the direct cost and indirect cost both
d) decreasing the direct cost and indirect cost both

Correct Answer – (B)

Question 7: 

The time corresponding to minimum total project cost is
a) crash time
b) normal time
c) optimistic time
d) between normal time and crash time

Correct Answer – (D)

Question 8: 

The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known as
a) total float
b) free float
c) interfering float
d) independent float

Correct Answer – (D)

Question 9: 

A father notes that when his teenage daughter uses the telephone, she takes not less than 6 minutes for a call and som? times as much as an hour. Fifteen minutes call are more frequent than calls of any other duration. If these phone calls were an activity in PERT project, then phone calls expected duration will be
a) 15 minutes
b) 20.143 minutes
c) 21 minutes
d) 27 minutes

Correct Answer – (C)

Question 10: 

Critical path
a) is always longest
b) is always shortest
c) may be longest
d) may be shortest

Correct Answer – (A)

MCQ Questions Civil Engineering Construction Planning and Management
MCQ Questions Civil Engineering Environmental Engineering

Multiple Choice Questions for Competitive Exams