MCQ Questions Civil Engineering Construction Planning and Management

MCQ Questions Civil Engineering Construction Planning and Management-5

MCQ Questions Civil Engineering Construction Planning and Management

Take a look at these MCQ Questions Civil Engineering Construction Planning and Management interview questions and our tips on how to answer them. If you’re applying for an engineering internship, graduate scheme or entry-level job, you’ll face at least one interview as part of an engineering employer’s recruitment process. You may be interviewed by one or more members of the HR team, senior members of the engineering team you’d be joining or a mixture of both. In this section we will study MCQ Questions Civil Engineering Construction Planning and Management. 
As well as questions about your reasons for applying to the role and the employer in question, engineering recruiters will be assessing your potential in the areas that is crucial to any engineering role: technical expertise. Engineers may be asked to perform feats of fantastic technical prowess, but it will be as as part of a Justice League rather than as a solo engineering super hero.
 

The interviewer is almost as nervous as the candidate in most interviews. You might wonder if you look confident enough, if you will hire the right person, or if you are asking the right engineering interview questions. The last question is arguably the most crucial part to worry about when you’re interviewing candidates. Other topics on Civil Engineering Multiple Choice Questions can be accessed 

MCQ Questions Civil Engineering Construction Planning and Management - Set - 5

Question 1: 

In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having
(A) Longest duration

(B) Highest cost slope

(C) Least cost slope

(D) Shortest duration

Correct Answer – (C)

Question 2 : 

A critical ratio scheduling
(A) Determines the status of each activity

(B) Adjusts automatically changes in activity progress

(C) Is a dynamic system

(D) None of these

 

Correct Answer – (D)

Question 3 : 

Critical path method
(A) Is an improvement upon bar chart method

(B) Provides a realistic approach to daily problems

(C) Avoids delays which are very common in bar charts

(D) All the above

 

Correct Answer – (D)

Question 4 : 

The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known as
(A) Total float

(B) Free float

(C) Interfering float

(D) Independent float

Correct Answer – (D)

Question 5 : 

Which of the following earth moving machines has the shortest cycle time?
(A) Drag line

(B) Hoe

(C) Clam shell

(D) Dipper shovel

Correct Answer – (D)

MCQ Questions Civil Engineering Construction Planning and Management

Question 6: 

For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is
(A) 8 days

(B) 9 days

(C) 10 days

(D) 15 days

Correct Answer – (B)

Question 7: 

At a work site, statistical quality control of concrete means
(A) Measurement of risks to eliminate failures

(B) Applying the theory’ of probability to sample testing or inspection

(C) Reduction in wastage of inspection costs

(D) Reduction in costs for the removal of defects

Correct Answer – (B)

Question 8: 

During the construction period, price variation clause in contracts caters to
(A) Increase in rates of only important materials

(B) Variation in cost in materials element, labour element and petrol-oil-lubricant element

(C) Variation in total cost of the project on an ad hoc basis

(D) Rate of inflation

Correct Answer – (B)

Question 9: 

Updating may result in
(A) Change of critical path

(B) Decrease of project completion time

(C) Increase of project completion time

(D) All of the above

Correct Answer – (D)

Question 10: 

Which of the following surfaces will give highest rolling resistance for a rubber tyred vehicle?
(A) Concrete

(B) Loose sand

(C) Asphalt

(D) Firm earth

Correct Answer – (B)

MCQ Questions Civil Engineering Construction Planning and Management
MCQ Questions Civil Engineering Environmental Engineering

Multiple Choice Questions for Competitive Exams