MCQ Questions Civil Engineering Construction Planning and Management
The interviewer is almost as nervous as the candidate in most interviews. You might wonder if you look confident enough, if you will hire the right person, or if you are asking the right engineering interview questions. The last question is arguably the most crucial part to worry about when you’re interviewing candidates. Other topics on Civil Engineering Multiple Choice Questions can be accessed
MCQ Questions Civil Engineering Construction Planning and Management - Set - 2
Question 1:
Free float for any activity is defined as the difference between
a) its earliest finish time and earliest start time for its successor activity
b) its latest start time and earliest start time
c) its latest finish time and earliest start time for its successor activity
d) its earliest finish time and latest start time for its successor activity
Correct Answer – (A)
Question 2 :
Total float for any activity is defined as the difference between
a) its latest finish time and earliest start time for its successor activity
b) its latest start time and earliest start time
c) its latest start time and earliest finish time
d) its earliest finish time and earliest start time for its successor activity
Correct Answer – (B)
Question 3 :
Free float is mainly used to
a) identify the activities which can be delayed without affecting the total float of preceding activity
b) identify the activities, which can be delayed without affecting the total float of succeeding activity
c) establish priorities
d) identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities
Correct Answer – (B)
Question 4 :
If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively
a) 3.5 and 5/6
b) 5 and 25/36
c) 3.5 and 25/36
d) 4 and 5/6
Correct Answer – (C)
Question 5 :
Latest start of an activity is always
a) greater than or equal to latest event time of preceding node
b) less than or equal to latest event time of preceding node
c) equal to latest event time of preceding node
d) less than latest event time of preceding node
Correct Answer – (A)
MCQ Questions Civil Engineering Construction Planning and Management
Question 6:
Select the incorrect statement.
a) A critical path always begins at the very first event.
b) A critical path always terminates at the last event.
c) Critical activities control the project duration.
d) Critical activity is the one for which free float is zero.
Correct Answer – (D)
Question 7:
Whenever an activity has zero total float, then
a) free float of the activity must be zero but independent float need not be zero
b) independent float must be zero but free float need not be zero
c) free float and independent float both must be zero
d) free float and independent float both need not be zero
Correct Answer – (C)
Question 8:
Select the incorrect statement.
a) Start float and finish float are always equal.
b) Total float can be either start float or finish float.
c) Start float and finish float need not be equal.
d) Start float and finish float are the differences between activity times and not event times
Correct Answer – (C)
Question 9:
If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then
a) expected time of activity A is greater than the expected time of activity B
b) expected time of activity B is greater than the expected time of activity A
c) expected time of both activities A and B are same
d) none of the above
Correct Answer – (C)
Question 10:
Select the incorrect statement.
a) Earliest start of an activity is the early event time of the node it leaves.
b) Latest finish of an activity is the late event time of the node it enters.
c) Latest start of an activity is its latest finish minus its duration.
d) none of the above
Correct Answer – (D)
- NCERT Solutions Class 12 Mathematics RD Sharma Sets : Exercise 1.1
- NCERT Solutions Class 12 Mathematics RD Sharma Sets : Exercise 1.2
- NCERT Solutions Class 12 Mathematics RD Sharma Sets : Exercise 1.3
- NCERT Solutions Class 12 Mathematics RD Sharma Sets : Exercise 1.4
- NCERT Solutions Class 12 Mathematics RD Sharma Trigonometric Functions : Exercise – 5.1
- NCERT Solutions Class 12 Mathematics RD Sharma Trigonometric Functions : Exercise – 5.2
- NCERT Solutions Class 12 Mathematics RD Sharma Trigonometric Functions : Exercise – 5.3
- NCERT Solutions Class 12 Mathematics RD Sharma Quadratic Equations : Exercise – 14.1
- NCERT Solutions Class 12 Mathematics RD Sharma Quadratic Equations : Exercise – 14.2
- NCERT Solutions Class 12 Mathematics RD Sharma Linear Inequations : Exercise – 15.1
- NCERT Solutions Class 12 Mathematics RD Sharma Linear Inequations : Exercise – 15.2
- NCERT Solutions Class 12 Mathematics RD Sharma Linear Inequations : Exercise – 15.3
- NCERT Solutions Class 12 Mathematics RD Sharma Linear Inequations : Exercise – 15.4
- NCERT Solutions Class 12 Mathematics RD Sharma Linear Inequations : Exercise – 15.5
- NCERT Solutions Class 12 Mathematics RD Sharma Linear Inequations : Exercise – 15.6
Multiple Choice Questions for Competitive Exams
- Multiple Choice Questions Class 12 Chemistry The Solid State
Set -1 Set -2 Set -3 Set -4 Set -5 - MCQ Questions Class 12 Solutions With Answers
Set -1 Set -2 Set -3 Set -4 Set -5 - MCQ Questions Class 12 Electrochemistry With Answers
Set -1 Set -2 Set -3 Set -4 Set -5 - MCQ Questions Class 12 Chemical Kinetics With Answers
Set -1 Set -2 Set -3 Set -4 Set -5 - MCQ Questions Class 12 Surface Chemistry With Answers
Set -1 Set -2 Set -3 Set -4 Set -5 - MCQ Questions Class 12 General Principles and Processes of Isolation of Elements With Answers
Set -1 Set -2 Set -3 Set -4 Set -5