MCQ Questions Civil Engineering Construction Planning and Management

MCQ Questions Civil Engineering Construction Planning and Management-2

MCQ Questions Civil Engineering Construction Planning and Management

Take a look at these MCQ Questions Civil Engineering Construction Planning and Management interview questions and our tips on how to answer them. If you’re applying for an engineering internship, graduate scheme or entry-level job, you’ll face at least one interview as part of an engineering employer’s recruitment process. You may be interviewed by one or more members of the HR team, senior members of the engineering team you’d be joining or a mixture of both. In this section we will study MCQ Questions Civil Engineering Construction Planning and Management. 
As well as questions about your reasons for applying to the role and the employer in question, engineering recruiters will be assessing your potential in the areas that is crucial to any engineering role: technical expertise. Engineers may be asked to perform feats of fantastic technical prowess, but it will be as as part of a Justice League rather than as a solo engineering super hero.
 

The interviewer is almost as nervous as the candidate in most interviews. You might wonder if you look confident enough, if you will hire the right person, or if you are asking the right engineering interview questions. The last question is arguably the most crucial part to worry about when you’re interviewing candidates. Other topics on Civil Engineering Multiple Choice Questions can be accessed 

MCQ Questions Civil Engineering Construction Planning and Management - Set - 2

Question 1: 

Free float for any activity is defined as the difference between
a) its earliest finish time and earliest start time for its successor activity
b) its latest start time and earliest start time
c) its latest finish time and earliest start time for its successor activity
d) its earliest finish time and latest start time for its successor activity

Correct Answer – (A)

Question 2 : 

Total float for any activity is defined as the difference between
a) its latest finish time and earliest start time for its successor activity
b) its latest start time and earliest start time
c) its latest start time and earliest finish time
d) its earliest finish time and earliest start time for its successor activity

Correct Answer – (B)

Question 3 : 

Free float is mainly used to
a) identify the activities which can be delayed without affecting the total float of preceding activity
b) identify the activities, which can be delayed without affecting the total float of succeeding activity
c) establish priorities
d) identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities

Correct Answer – (B)

Question 4 : 

If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively
a) 3.5 and 5/6
b) 5 and 25/36
c) 3.5 and 25/36
d) 4 and 5/6

Correct Answer – (C)

Question 5 : 

Latest start of an activity is always

a) greater than or equal to latest event time of preceding node
b) less than or equal to latest event time of preceding node
c) equal to latest event time of preceding node
d) less than latest event time of preceding node

Correct Answer – (A)

MCQ Questions Civil Engineering Construction Planning and Management

Question 6: 

Select the incorrect statement.
a) A critical path always begins at the very first event.
b) A critical path always terminates at the last event.
c) Critical activities control the project duration.
d) Critical activity is the one for which free float is zero.

Correct Answer – (D)

Question 7: 

Whenever an activity has zero total float, then
a) free float of the activity must be zero but independent float need not be zero
b) independent float must be zero but free float need not be zero
c) free float and independent float both must be zero
d) free float and independent float both need not be zero

Correct Answer – (C)

Question 8: 

Select the incorrect statement.
a) Start float and finish float are always equal.
b) Total float can be either start float or finish float.
c) Start float and finish float need not be equal.
d) Start float and finish float are the differences between activity times and not event times

Correct Answer – (C)

Question 9: 

If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then

a) expected time of activity A is greater than the expected time of activity B
b) expected time of activity B is greater than the expected time of activity A
c) expected time of both activities A and B are same
d) none of the above

Correct Answer – (C)

Question 10: 

Select the incorrect statement.
a) Earliest start of an activity is the early event time of the node it leaves.
b) Latest finish of an activity is the late event time of the node it enters.
c) Latest start of an activity is its latest finish minus its duration.
d) none of the above

Correct Answer – (D)

MCQ Questions Civil Engineering Construction Planning and Management
MCQ Questions Civil Engineering Environmental Engineering

Multiple Choice Questions for Competitive Exams