MCQ Questions Civil Engineering Airport Engineering

MCQ Questions Civil Engineering Airport Engineering-3

MCQ Questions Civil Engineering Airport Engineering

Take a look at these MCQ Questions Civil Engineering Airport Engineering interview questions and our tips on how to answer them. If you’re applying for an engineering internship, graduate scheme or entry-level job, you’ll face at least one interview as part of an engineering employer’s recruitment process. You may be interviewed by one or more members of the HR team, senior members of the engineering team you’d be joining or a mixture of both. In this section we will study MCQ Questions Civil Engineering Airport Engineering. 
As well as questions about your reasons for applying to the role and the employer in question, engineering recruiters will be assessing your potential in the areas that is crucial to any engineering role: technical expertise. Engineers may be asked to perform feats of fantastic technical prowess, but it will be as as part of a Justice League rather than as a solo engineering super hero.
 

The interviewer is almost as nervous as the candidate in most interviews. You might wonder if you look confident enough, if you will hire the right person, or if you are asking the right engineering interview questions. The last question is arguably the most crucial part to worry about when you’re interviewing candidates. Other topics on Civil Engineering Multiple Choice Questions can be accessed 

MCQ Questions Civil Engineering Airport Engineering - Set - 3

Question 1: 

Which of the following is an example of failure in flexible pavements ?
a) Alligator cracking
b) Mud pumping
c) Warping cracks
d) Shrinkage cracks

Correct Answer – (A)

Question 2 : 

For supersonic transport aircraft, the minimum turning radius of taxiway is
a) 60 m
b) 120 m
c) 180 m
d) 240 m

Correct Answer – (C)

Question 3 : 

Assertion A : Airport capacity during IFR conditions is usually less than that during VFR conditions.
Reason R: During clear weather condition (VFR), the aircrafts on final approach to runway can be spaced closer during poor visibility conditions.
Select your answer based on the coding system given below:
a) Both A and R are true and R is the correct explanation of A
b) Both A and R are true but R is not the correct explanation of A
c) A is true but R is false
d) A is false but R is true

Correct Answer – (A)

Question 4 : 

The centre to centre spacing of heliport lighting along the periphery of landing and take off area should be
a) 2.5 m
b) 5.0 m
c) 7.5 m
d) 10.0 m

Correct Answer – (C)

Question 5 : 

In Intrumental landing system, the middle markers are located
a) along the extended centre line of runway end
b) about 1 km. ahead of the runway threshold
c) at the runway threshold
d) about 7 km. ahead of the runway threshold

Correct Answer – (B)

MCQ Questions Civil Engineering Airport Engineering

Question 6: 

As per UK design criteria, if LCN of aircraft is between 1.25 to 1.5 times the LCN of pavement, then the number of movements allowed are
a) Zero
b) 300
c) 3000
d) Unrestricted

Correct Answer – (B)

Question 7: 

Assertion A: The width of a taxiway is smaller than the runway width. Reason R:The speed of the aircraft on a taxiway is greater than that on runway. Select your answer based on coding system given below
a) Both A and R are true and R is the correct explanation of A
b) Both A and R are true but R is not the correct explanation of A
c) A is true but R is false
d) A is false but R is true

Correct Answer – (C)

Question 8: 

The slope of the obstruction clearance line from the boundary of the heliport should be
a) 1:2
b) 1:5
c) 1:8
d) 1:40

Correct Answer – (C)

Question 9: 

The size of landing area for multi-engined helicopters operating under 1FR conditions is
a) 22.5 m x 22.5 m
b) 30 m x 30 m
c) 22.5 m x 30 m
d) 60 mx 120 m

Correct Answer – (D)

Question 10: 

The width and interval of transverse centre line bars along the extended centre line of runway, in approach lighting system are
a) 3 m and 30 m
b) 4.2 m and 30 m
c) 4.2 m and 50 m
d) 3 m and 45 m

Correct Answer – (B)

MCQ Questions Civil Engineering Airport Engineering
MCQ Questions Civil Engineering Concrete Technology and Design of Concrete Structures

Multiple Choice Questions for Competitive Exams